Kamehameha and Hina Avenue Pavement Rehab

Scope of Work
The project includes rehabilitation of the Kamehameha Avenue Pavement Structure from Puunene Avenue to Papa Avenue and Hina Avenue pavement structure from Wakea Avenue to Niihau Street and Molokai Akau Street to Ani Street with Asphalt Concrete, Hot Mix Asphalt Base, and Aggregate Sub base section; replacement/reconstruction of concrete sidewalks and concrete curbs; installation of pavement striping and markers; and other incidental items.
(MAP)

When
NTP (Notice to Proceed) – August 26, 2013
Completion Date - June 30,2014
Contract Working Days: 210 Working Days


Streets Involved
Kamehameha Avenue Pavement Rehabilitation - Puunene Avenue to Papa Avenue
Hina Avenue - Wakea Avenue to Niihau Street and Molokai Akau Street to Ani Street

Contractor
Maui Master Builders
72 Ting’s Drive,
Wailuku HI, 96793

Contract Cost
$3,478,272.43